The company Krnovo Green Energy, which is in charge of the construction and operation of Krnovo wind farm, announced that 20 of 26 planned wind turbines have been installed so far at the construction site.
The representatives of the company explained that bad weather, accompanied by rain and wind have slowed the construction works, but the works still progress according to plan. It is expected that the remaining six wind turbines will be set up within a month, if weather conditions permit.