Report on Cernavoda-Stalpu transmission line project – Romania, 26 May 2020
Romanian electricity transmission system operator Transelectrica said that the first two and a half months of works on the construction of 400 kV Cernavoda-Stalpu double-circuit overhead transmission line a total […]