Tag: Moglice

Statkraft commissioned HPP Moglice – Albania, 23 June 2020

Norwegian company Statkraft said that it has started the commercial operation of its hydropower plant Moglice, a part of the Devoll hydro project. Statkraft CEO Christian Rynning-Tonnesen said that finalizing […]

HPP Moglice to be commissioned in Q2 2020 – Albania, 14 April 2020

Norwegian company Statkraft said that hydropower plant Moglice is expected to be commissioned in the second quarter of the year. The statement from the company said that all construction works […]

HPP Moglice to be put into operation in spring 2020 – Albania, 15 January 2020

Norwegian company Statkraft said that hydropower plant Moglice is expected to start production in the spring of this year, adding that the plant’s testing is currently underway. The filling of […]